Water Infrastructure
Dar Al-Salam Water Project (Sq 5 & 10) & 12" Transmission Line
Dar Al-Salam (Squares 5 and 10), Khartoum State

Verified Project Photography • Al Mofon Profile
Project Overview
Execution of comprehensive water distribution works in Dar Al-Salam including internal grid distribution in Squares 5 and 10 alongside a dedicated 12-inch transmission main.
Expanded access to clean piped water in high-density suburban communities.
Scope of Work
Distribution network construction for Dar Al-Salam Squares 5 and 10
Installation of heavy 12-inch transmission line
Interconnections, valve chambers, and flow distribution points
Technical Specifications
Transmission Diameter12 inch
Sectors CoveredSquares 5 and 10
VERIFIED RECORD
This project was executed by Al Mofon Foundation in compliance with contract specifications.
Project Details
Sector Category:Water Infrastructure
Location:Dar Al-Salam (Squares 5 and 10), Khartoum State
Client / Partner:[Client details retained in project dossier]
Other Documented Projects
Water InfrastructureDrilling & Construction of Two Water Yards in West DarfurWest Darfur State (Sirba Locality: Manzola Site & Sawani Site)Water InfrastructureDrilling of 3 Deep Boreholes in Central & West DarfurCentral Darfur and West Darfur StatesWater InfrastructureAl-Thawra Water Network Replacement (30+ Km HDPE)Al-Thawra, Omdurman, Khartoum State
INSTITUTIONAL PARTNERSHIPS
LET'S BUILD THE FUTURE TOGETHER
Discuss your next engineering, construction, or water infrastructure project with our experienced multi-disciplinary team.
AL MOFON FOUNDATION FOR MULTI ACTIVITIES CO. LTD. • EST. 2010